Unfinished installs
Panels on your roof, but they were never turned on?
It happens more than you'd think. The installer leaves before the final inspection or the utility hookup, and the system just sits there while the loan payments continue. The panels are usually fine. The job just isn't finished.
- We check your permit status with the city or township
- Fix what failed inspection and get it re-inspected
- Handle the utility's approval to switch it on
Get your solar working again
Tell us what's going on. We'll call you, usually within one business day.
Why systems never get switched on
A home solar system needs two approvals before it's allowed to run: your city or township's final inspection of the electrical work, and your utility's permission to operate, which usually comes after that inspection passes. If the installer closed, ran out of money or simply stopped calling back, one or both never happened.
How to tell if yours was ever turned on
- Your electric bill never changed after the panels went up.
- The inverter is dark, or shows an error, on a sunny afternoon. Some systems were left with the solar breaker or disconnect switched off.
- The monitoring app shows nothing, or was never set up for you.
- You never received approval from the utility, the letter or email saying your system may operate.
- Your electric meter was never changed or reprogrammed. Utilities usually need a meter that can measure power going both ways.
How to check your permit
Your city or township building department has the permit record. Many West Michigan cities let you look it up online by address: Grand Rapids through its Accela Citizen Access portal, and many others through BS&A Online. Here's what the status usually means:
| Permit status | What it usually means |
|---|---|
| Finaled, or final inspection approved | The city signed off. If the system still isn't running, the problem is likely with the utility or the equipment. |
| Expired, or closed without a final inspection | The inspection never happened. The work likely needs a new permit and inspection. |
| Open, or inspection failed | Something was flagged and never fixed, or the inspection was never scheduled. |
| No permit found | The work may never have been permitted. It can usually still be permitted and inspected now. |
Not sure how to read it? Send us your address and we'll look it up.
What usually needs fixing
Unfinished systems tend to fail on the same handful of things:
- Missing warning labels and placards required on solar equipment
- Rapid shutdown equipment that wasn't installed or doesn't work
- Grounding and bonding of the racking and panels
- Wiring that isn't secured or protected, or conduit that wasn't finished
- A missing or wrongly placed disconnect switch
- The solar connection at your electrical panel, such as breaker sizing
- Paperwork the inspector or utility needs, like plans and equipment spec sheets
Most of this is a day or two of work. It's usually a small fraction of what the system cost.
Can I just turn it on myself?
No. Running a grid-connected system without the utility's approval breaks your interconnection agreement. An uninspected system may also be unsafe for you and for line workers. Get it inspected and approved first.
How long it takes
The repairs are usually quick. Most of the time goes to scheduling the inspection and waiting for the utility, often a few weeks in total. We handle both and tell you where it stands.
Installed by a company that closed? Climax Solar and Pink Energy left many systems in exactly this state. What happens when your solar company goes out of business.
How it works
- Tell us what's wrong. Two minutes on the form above.
- We call you. We'll ask about your system and set up a visit.
- We find the problem and quote the fix before any work starts.
- Your panels make power again. No more paying for a system that sits there.
We work on systems other companies abandoned
When an installer goes out of business, the homeowner is often left with no one to call: no monitoring, no workmanship warranty, sometimes a permit that never got its final inspection. The panels and inverters themselves usually still carry the manufacturer's warranty, and we can help you use it.
Common questions
Why were my solar panels never turned on?
A system needs a final inspection from your city or township and permission to operate from your utility. If the installer left before either step, the system was never approved to run.
How do I know if my solar permit passed final inspection?
Look up your address on your city or township's permit site, or call the building department. A status of finaled or final approved means it passed. Expired, closed without a final, or open usually means it never did. We can check it for you.
Can I turn my solar panels on myself?
No. Running a grid-connected system without your utility's approval breaks your interconnection agreement, and an uninspected system may be unsafe. Get it inspected and approved first.
How long does it take to get an unfinished solar system turned on?
The repairs are usually a day or two. Scheduling the inspection and getting utility approval often takes a few weeks in total.
Can someone else finish my solar installation?
Yes. A licensed installer can fix what the inspector flagged, schedule a new inspection and complete the utility paperwork.